© 2024

620 Egan Way Kodiak, AK 99615
907-486-3181

Kodiak Public Broadcasting Corporation is designated a tax-exempt organization under section 501(c)(3) of the Internal Revenue Code. KPBC is located at 620 Egan Way, Kodiak, Alaska. Our federal tax ID number is 23-7422357.

LINK: FCC Online Public File for KMXT
LINK: FCC Online Public File for KODK
LINK: FCC Applications
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

MV Tustumena replacement ferry setback, possibly years, as project awaits construction

Courtesy of the Alaska Department of Transportation A rendering of the Tustumena Replacement Vessel.
The Alaska Department of Transportation
/
Alaska Department of Transportation
A rendering of the Tustumena Replacement Vessel.

Ferry passengers will have to wait even longer to sail on the Tustumena replacement vessel [TRV]. The more than $300 million project is not expected to be completed until at least the end of 2028 – a year later than originally anticipated.

Earlier this year the Alaska Marine Highway System (AMHS) had been estimating the new mainliner ferry would be done in 2027. But during an AMHS operations board meeting on Oct. 23, Director Craig Tornga said a Federal Transit Authority (FTA) funding audit and long checklist of requirements has slowed things down.

“We’re still working through the programmatic side with the FTA," Tornga explained. "We’re getting close. The FTA has commented that we’d have pre-award authority for all of the Tustumena funding by the end of the year.”

Once AMHS is given pre-award authority, Tornga said that essentially means then the Tustumena Replacement Project will be authorized to start soliciting bids.

Glosten, an architecture firm which has an office in Seattle, completed the final design for the replacement vessel back in 2022, but the project has yet to go out to bid for construction. The Request for Proposals, or RFP, was expected to go out much earlier this year and construction could’ve begun by December. Now, Tornga said that won’t happen till later this month, or by the end of 2024.

That means the new Tustumena won’t likely be in service until 2030, making the aging vessel 66-years-old by the time it is fully retired. Tornga said there are several shipyards that have expressed interest in building the new TRV. The new vessel would be one of potentially several hybrid-electric ferries AMHS plans to have constructed in the coming years as part of its long-range plan.

The replacement vessel is set to be bigger than the existing Tustumena, carry 250 passengers, and up to 58 vehicles. In conjunction with the TRV project, the Alaska Marine Highway System is also looking to upgrade some of its ferry terminals and infrastructure at various coastal locations across the state.

Meanwhile the current Tusty vessel is in the midst of its scheduled winter sailings. The ferry’s last trip to Kodiak of the season is scheduled to arrive from Homer on New Year’s Day and depart for the last time that same evening.

After that the vessel goes into its annual overhaul where it will receive much needed maintenance from January until April of 2025.

Davis Hovey was first drawn to Alaska by the opportunity to work for a radio station in a remote, unique place like Nome. More than 7 years later he has spent most of his career reporting on climate change and research, fisheries, local government, Alaska Native communities and so much more.
Related Content